Under Construction - Gateway Court Townhomes Shakopee, MN

Despite the cold weather conditions, we have (9) nine buildings under various stages of construction.

The first townhome has progressed to the finish stages for both interior and exterior work. The remainder are following right along with an average of a 2-week stagger in their schedules. We anticipate being in a position for occupancy in the first (3) three units in May. The Owner’s Management team is already accepting applications for spring move-ins.

Needless to say, with the number of buildings and varied stages of construction we typically have as many as 75 workers on site performing everything from framing to shingles, siding drywall and soon painting and finishing carpentry.